Construction Zone

2017 Projects

Road Resurfacing Project: Shaker Boulevard Repaving

Beginning Monday, April 10, repaving of Shaker Boulevard will begin. Anticipated completion is early November, weather permitting.

There are four phases to the project and during each phase, Shaker Boulevard will be closed in both directions, east- and westbound, to through traffic. North- and southbound roads at Shaker Blvd. will also be closed during each phase.

  • Phase 1:Coventry to Lee (late May - mid July)
  • Phase II: Warrensville Ctr. to Green (late May - mid July)
  • Phase III: Green to Sulgrave (mid July - mid August)
  • Phase IV: Lee to Warrensville Ctr. (mid August - early November)

On-street parking between 7 am and 6 pm will be prohibited. Permits for side street parking during these hours will be distributed to residents along Shaker Boulevard.

Motorists are advised to find alternate east/west routes through the City for the duration of the project. All dates are approximate as the timing of each phase is dependent upon the weather. Expect heavy traffic on South Woodland in particular.

We apologize for the inconvenience caused by this project. If you have questions, please contact Ronyak Paving at 440-834-1988 or the Construction Manager at 216-776-6806.

Green Lake Dredging Project: Parkland Road Closure

Beginning Thursday, February 22, Parkland between Attleboro and Lee will be closed to through traffic. Local access will be maintained in the eastbound lane only. This portion of Parkland will be closed until the end of the summer. The closure is due to the dredging of Green Lake, a project of the Northeast Ohio Regional Sewer District (NEORSD). 

We apologize for any inconvenience caused by this project. If you have questions, please call NEORSD at 216-881-8247. Thank you for your patience. 

 

Sign up for City Announcements to receive updates.

Monday, April 24, 2017