Road Resurfacing Project: Shaker Boulevard Repaving

Beginning Monday, April 10, repaving of Shaker Boulevard will begin. Anticipated completion is early November, weather permitting.

There are four phases to the project and during each phase, Shaker Blvd. will be closed in both directions, east- and westbound, to through traffic. North- and southbound roads at Shaker Blvd. will also be closed during each phase.

Phase I: Coventry to Lee (Complete)
Phase II: Green to Sulgrave (Complete)
Phase III: Warrensville Ctr. to Green (Complete)
Phase IV: Lee to Warrensville Ctr. (week of July 24 - mid-October)

On-street parking between 7 am and 6 pm will be prohibited. Permits for side street parking during these hours will be distributed to residents along Shaker Blvd.

Motorists are advised to find alternate east/west routes through the City for the duration of the project. All dates are approximate as the timing of each phase is dependent upon the weather. Expect heavy traffic on South Woodland in particular.

We apologize for the inconvenience caused by this project. If you have questions, please contact Ronyak Paving at 440-834-1988 or the Construction Manager at 216-776-6806.

Updated: May 11, 2017